scrum psm-i practice test

Professional Scrum Master I Exam

Last exam update: Jul 20 ,2024
Page 1 out of 13. Viewing questions 1-15 out of 197

Question 1

When is implementation of a Product Backlog item considered complete?

  • A. At the end of the Sprint.
  • B. When the item has no work remaining in order to be potentially released.
  • C. When Quality Assurance reports that the item passes all acceptance criteria.
  • D. When all work in the Sprint Backlog related to the item is finished.
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 2

Which two ways of creating Development Teams are consistent with Scrum’s values? (Choose two.)

  • A. Existing teams propose how they would like to go about organizing into the new structure.
  • B. Managers personally re-assign current subordinates to new teams.
  • C. Managers collaborate to assign individuals to specific teams.
  • D. Bring all the developers together and let them self-organize into Development Teams.
  • E. The Chief Product Owner determines the new team structures and assignments.
Answer:

A D

User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
vote your answer:
A
B
C
D
E
0 / 1000

Question 3

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date
based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was
13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the
plan, figured that a velocity of 17 was within their reach.
A good way to continue is:

  • A. The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.
  • B. Add enough people to the Development Team for the deadline to be made.
  • C. The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Masters duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.
  • D. The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 4

Why does the Product Owner want the Development Team to adhere to its definition of “Done”?

  • A. To have complete transparency into what has been done at the end of each Sprint.
  • B. To be able to reprimand the team when they don’t meet their velocity goal for the Sprint.
  • C. To know what the team will deliver over the next three Sprints.
  • D. To predict the team’s productivity over time.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 5

How do you know that a Scrum Team is cross-functional? (Choose the best answer.)

  • A. Scrum Team has all the skills to create an increment by the end of every Sprint.
  • B. A few of the Development Team members pair program and do Test Driven Development.
  • C. There are no conflicts within the Scrum Team.
  • D. Every member of the Scrum Team is able to perform every task.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 6

What is the recommended size for a Development Team?

  • A. 7 plus or minus 3.
  • B. At least 7.
  • C. 9.
  • D. 3 to 9.
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 7

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

  • A. Run the Daily Scrum.
  • B. Prioritize the Development Team’s work on the Sprint Backlog.
  • C. Update management on what is being worked on.
  • D. Answer questions from the Development Team about items in the current Sprint.
Answer:

C D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 8

When does the next Sprint begin?

  • A. When the Product Owner is ready.
  • B. Immediately after the conclusion of the previous Sprint.
  • C. The Monday following the Sprint Review.
  • D. Immediately following the next Sprint Planning.
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 9

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

  • A. True
  • B. False
Answer:

A

User Votes:
A
50%
B
50%
Discussions
vote your answer:
A
B
0 / 1000

Question 10

Which of the following are roles on a Scrum Team? (Choose three.)

  • A. Users
  • B. Scrum Master
  • C. Product Owner
  • D. Development Team
  • E. Customers
Answer:

B C D

User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
vote your answer:
A
B
C
D
E
0 / 1000

Question 11

Multiple Scrum Teams working on the same project must have the same Sprint start date.

  • A. True
  • B. False
Answer:

B

User Votes:
A
50%
B
50%
Discussions
vote your answer:
A
B
0 / 1000

Question 12

How much of the Sprint Backlog must be defined during the Sprint Planning event?

  • A. Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
  • B. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
  • C. Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
  • D. Just enough to understand design and architectural implications.
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 13

Which of the following are true about the Product Owner role? (Choose two.)

  • A. The Product Owner is one person.
  • B. The Product Owner is accountable for ordering the Product Backlog.
  • C. Multiple people can share the Product Owner role on a Scrum Team.
  • D. The Product Owner role can be played by a committee or a team of people.
Answer:

A B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 14

Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)

  • A. True. Outcomes affected by their participation and availability.
  • B. False. A Product Owner can be replaced by a subject matter expert in the Scrum Team.
  • C. False. A Scrum Master is only required when asked for by the Scrum Team.
  • D. True. Each must be 100% dedicated to the Scrum Team.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 15

When must a Product Owner release each Increment? (Choose the best answer.)

  • A. When it makes sense.
  • B. When the Scrum Team finishes their work.
  • C. Whenever the product is free of defects.
  • D. After every Sprint, Without exception.
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000
To page 2