When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct answers to
this question.
A B
What solution operations framework can customers use to create a joint business and IT
organization?
B
What activity do you perform in the Deploy phase?
B
What are some of the key characteristics of the implementation approach in the SAP Activate
methodology? Note: There are 2 correct answers to this question.
B D
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make
forecasts based on actual data?
C
What are some of the key topics covered in the Customer Team Enablement workstream? Note:
There are 2 correct answers to this question.
A B
You are defining the testing strategy for your project.
What would you include in a scope of Integration Test? Note: There are 2 correct answers to this
question.
A D
Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct answers to
this question.
A C D
In which phase do you create "an ordered list of everything that is known to be needed in the
product"?
D
What is an activity that is performed at the end of the Realize phase?