A customer needs to analyze the capacity requirements of their network activities. Which reports do
you recommend? Note: There are 2 correct answers to this question
A, D
Explanation:
Resource reports and hierarchical reports are some of the possible reports that you can use to
analyze the capacity requirements of your network activities. Resource reports display capacity
requirements and availability for work centers or resources over a period of time. Hierarchical
reports display capacity requirements and availability for work centers or resources in a hierarchical
structure,
such
as plant,
MRP
controller,
or work
center group.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
You are using WBS elements and activities are NOT assigned. Which statements apply to the
maintenance of the actual start and finish? Note: There are 2 correct answers to this question
BC
Explanation:
If you are using WBS elements and activities are not assigned, you can always maintain the actual
start and finish date of a WBS element manually or automatically. However, you can only maintain
the actual start if the WBS element has the status “Released” or “Partially released”, which means it
is ready for processing or partially ready for processing. You can maintain the actual finish regardless
of
the
status
of
the
WBS
element.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
What functions are available for period end closing in SAP Project System? Note: There are 3 correct
answers to this question
A, D, E
Explanation:
Settlement, progress analysis, and results analysis are some of the functions available for period end
closing in SAP Project System. Settlement is used to allocate the costs and revenues in projects or the
results analysis data to one or more receivers, such as cost centers, profitability segments, or assets.
Progress analysis is used to determine and compare the planned and actual project progress values,
based on the overall planned costs and the work done. Results analysis is used to perform a periodic
valuation of the project, based on the costs and revenues expected or incurred in the project.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to
this question
A, C, E
Explanation:
User status profiles are used to define additional statuses for project objects that can control their
business processes. You can assign user status profiles for WBS elements in the project profile, which
is a template for creating projects with similar characteristics. You can also assign user status profiles
for WBS elements in the project type, which is a classification of projects according to their
objectives and characteristics. You can also assign user status profiles for WBS elements in the
operative WBS element itself, which is a structural element of a project that represents a task or a
partial task. Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Which organizational structures are required for network activities? Note: There are 3 correct
answers to this question
A, B, D
Explanation:
Controlling area, plant, and company code are some of the organizational structures required for
network activities. Controlling area is an organizational unit that represents a closed system for cost
accounting purposes. Plant is an organizational unit that represents a location where materials are
produced or services are provided. Company code is an organizational unit that represents an
independent accounting entity with its own balance sheet and profit and loss statement. Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this
question
A, D
Explanation:
Basic dates and planned dates are some of the sets of dates that can be used to schedule networks.
Basic dates are the earliest possible start and finish dates of an activity or a network, based on its
dependencies and constraints. Planned dates are the scheduled start and finish dates of an activity or
a
network,
based
on
its
basic
dates
and
available
capacities.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct
answers to this question
AB
Explanation:
Sales order and billing are some of the sales documents that can update planned revenues on WBS
elements. Sales order is a document that records a customer’s request for goods or services from a
sales organization. Billing is a document that records the delivery of goods or services to a customer
and requests payment for them. Both sales order and billing can update planned revenues on WBS
elements if they are assigned to them directly or indirectly via network activities. Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
You want to determine the planned costs for an internally processed activity. Which data do you
need Note: There are 2 correct answers to this question
A, B
Explanation:
To determine the planned costs for an internally processed activity, you need the duration and
activity type data. The duration is the time required to complete the activity. The activity type is a
classification of activities according to their functions or characteristics. The system calculates the
planned costs for an internally processed activity based on the formula for costing in the work center,
the activity output price for the activity type and cost center assigned to the work center, and the
duration
of
the
activity.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to
this question
B, C, E
Explanation:
Project simulations are some of the advantages of using project simulations in SAP Project System.
Project simulations are copies of projects that allow you to plan and simulate different scenarios
without affecting operational projects. Project simulations can be created without using an
operational project as a template, which means you can start from scratch or use a standard
structure. Project simulations can be used to plan structures and costs, which means you can create
and change WBS elements, networks, activities, and cost elements. Multiple project simulations can
be used simultaneously, which means you can compare different alternatives and choose the best
one.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct
answers to this question
AD
Explanation:
Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project
System. Planned revenue requires a sales order assigned to a WBS element, which means that the
sales order item contains the data for revenue planning, such as quantity, price, and billing plan.
Actual revenue is posted via a billing document created from a sales order, which means that the
billing document records the delivery of goods or services to a customer and requests payment for
them.
Reference:
https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html