Question 1
What is the key characteristics of the agile project approach
A.
Formal and detailed documentation
B.
Iterative build with frequent inspections
C.
Frequent Quality Gates
D.
Frequent and detailed project scheduling
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
What tool is used to synchronize changes between SAP ERP and SAP S/4HANA maintenance tracks?\
A.
Retrofit
B.
Business process change analyser
C.
SAP code inspector
D.
SAP code vulnerability analyser
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
Which of the following tools are specific to the data management workstream? There are 3 correct answers to this question.
A.
SAP data services
B.
SAP landscape transformation
C.
SAP roadmap viewer
D.
SAP solution manager
E.
SAP S/4HANA Migration cockpit (for both SAP S/4HANA CLOUD & SAP S/4 HANA EDITIONS)
Answer:
A, D, E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 4
Which activity helps the project team add user stories to the product backing?
A.
Preparing a project schedule
B.
Planning the user acceptance test
C.
Conducting the solution validation workshop
D.
Assessing project risks
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
What is scrum of scrum?
A.
Alternative to regular scrum process for smaller teams
B.
Frequent inspections of code and configuration prior to quality gates
C.
Mechanism for gathering and validating requirements
D.
Integration meeting between the various project teams
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 6
Preliminary strategy developed by the customer to approach the project in a specific workstream
A.
Optional information that is NOT important for project activities
B.
Approach document that is developed by a united project team (partner+ customer)
C.
Preliminary strategy developed by the customer to approach the project in a specific workstream
D.
Project result that is developed solely by the partner
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
In which phase should you first run the SAP readiness check for SAP S/4HANA In a "selective data transition" transition path, in a system consolidation scenario That includes conversions from SAP ERP?
A.
Explore
B.
Discover
C.
Prepare
D.
Realize
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 correct answers to this question.
A.
Solution review for waves
B.
Solution demo for sprints
C.
User acceptance test
D.
Demo the SAP model company
Answer:
A, B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
What accelerator can help you document the configuration definition in the explore Phase?
A.
Backlog template
B.
Data definition
C.
Change request template
D.
Test strategy
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
What is the order of artifacts within the technical architecture and infrastructure workstream In the prepare phase?
A.
Technical strategy>hardware specification from hardware vendor>parameters hardware seizing Calculation>hardware seizing work B. Hardware specification from hardware vendor>parameter's hardware seizing calculation>hardware seizing result>technical strategy work
C.
Hardware specification from hardware vendor>technical strategy>parameter's hardware seizing Calculation>hardware seizing
D.
Technical strategy>parameter's hardware>seizing calculation>hardware seizing results>Hardware specification from hardware vendor
Answer:
D
User Votes:
A
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
What sprint types are part of the SAP activate methodology There are 3 correct answers to this question.
A.
Initial
B.
Daily
C.
Foundational
D.
Firm-up
E.
Build
Answer:
C, D, E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 12
Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project.
A.
Change request management
B.
Requirement management
C.
Focused build
D.
Solution manager test suite
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
In which phase should you create a data migration strategy (LO) during a selective data transition?
A.
Deploy
B.
Discover
C.
Realise
D.
Explore
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 14
Ready-to-use Content in SAP Activate incudes which of the following There are 2 correct answers to this question
A.
Project Accelerators
B.
SAP Best Practices
C.
Courses delivered by SAP Education
D.
Business Models from leading companies in each industry sector
Answer:
A, B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
What are some of the key topics covered in the customer team enablement workshops? There are 3 correct answers to this question.