Which of the following considerations apply when determining the project methodology? Note:
There are 3 correct answers to this question.
B, D, E
Explanation:
Determining the project methodology requires evaluating the organizational fit to ensure the
methodology aligns with the company's culture, the integration fit for technical compatibility, and
the project fit to meet specific project requirements. These criteria help select a methodology that
supports project success.
Reference: SAP Activate Methodology Selection Guide, Project Methodology Considerations
What is the difference between the "New Implementation of SAP S/4HANA Cloud, public edition"
and the "New Implementation of SAP S/4HANA, private edition" transition paths? Note: There are 2
correct answers to this question.
A, D
Explanation:
The "New Implementation of SAP S/4HANA Cloud, public edition" leverages SAP Central Business
Configuration for guided setup, while the private edition uses the IMG for configuration. The public
edition follows a SAP-controlled upgrade schedule, whereas the private edition allows for customer-
specific upgrade timelines.
Reference: SAP Activate, Transition Paths for SAP S/4HANA Cloud
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA
Cloud, public edition" transition path?
D
Explanation:
In the SAP Activate methodology, the fit-to-standard workshop is a crucial component of the Explore
phase, especially in the context of the SAP S/4HANA Cloud, public edition. This workshop helps
validate standard processes against business requirements and is foundational to solution design.
Reference: SAP Activate, Explore Phase, Fit-to-Standard Workshop Guidelines
Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2
correct answers to this question.
B, D
Explanation:
The Business-Driven Configuration questionnaire helps gather business requirements relevant to
SAP Best Practices, while the Requirements feature in SAP Cloud ALM supports capturing
requirements and gaps identified in fit-to-standard workshops. Both accelerators streamline the
process of configuring the system to meet business needs.
Reference: SAP Activate, Explore Phase Accelerators, Fit-to-Standard Workshop Tools
Which of the following are capabilities of the test automation tool for SAP S/4HANA Cloud, public
edition? Note: There are 2 correct answers to this question.
B, D
Explanation:
The SAP S/4HANA Cloud test automation tool enables custom test automation creation and captures
test results with screenshots for better documentation and analysis. These features enhance
automated testing efficiency within SAP S/4HANA Cloud projects.
Reference: SAP Activate, Test Automation Tools for SAP S/4HANA Cloud, Automated Testing
Capabilities
What accelerator can help you document the configuration definition in the Explore phase?
D
Explanation:
The backlog template is used in the Explore phase to document and track configurations and
requirements identified during workshops. It serves as a reference for configuration activities and
aligns with Agile practices by maintaining a structured list of needed changes and customizations.
Reference: SAP Activate, Explore Phase Documentation, Configuration Documentation Templates
Which of the following characteristics are mandatory with SAP S/4HANA Cloud, public edition? Note:
There are 2 correct answers to this question.
A, C
Explanation:
SAP S/4HANA Cloud, public edition is designed to have SAP-managed software upgrades to ensure
consistent quality and performance. Additionally, SAP Best Practices activation is mandatory to
ensure a standardized, streamlined implementation.
Reference: SAP Activate, SAP S/4HANA Cloud Characteristics, Upgrade and Best Practices
Requirements
What activity do you perform during the daily stand-up meeting?
D
Explanation:
The daily stand-up meeting is focused on team alignment, with members reporting any roadblocks
(or "showstoppers") that hinder their progress. This activity ensures timely identification and
resolution of issues affecting sprint goals.
Reference: SAP Activate Agile Project Delivery, Daily Stand-Up Meeting Practices
What criteria does the product owner use to sequence the backlog? Note: There are 2 correct
answers to this question.
A, D
Explanation:
The product owner sequences backlog items primarily based on business priority to deliver the
highest value first, while also considering technical dependencies to prevent development delays.
This approach optimizes the team's efficiency in delivering value.
Reference: SAP Activate Product Backlog Management, Sequencing and Prioritization Criteria
Who determines the tasks that are required to complete the committed backlog items in a Sprint?
C
Explanation:
In Agile methodology, the Scrum team self-organizes to determine the specific tasks needed to
complete backlog items. This autonomy encourages accountability and collaboration among team
members to achieve sprint goals.
Reference: SAP Activate Agile Project Delivery, Task Determination in Sprint Planning