Which is a task of product-based planning?
B
Which role is responsible for creating Checkpoint Reports?
B
How many management stages should a PRINCE2 project consist of?
C
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team
Manager.
C
What product would enable the Project Manager to review how a Work Package is performing
against its cost tolerance?
D
Which is a true statement about PRINCE2 event-driven controls
C
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the
project's plans
C
Identify the missing words in the following sentence. A risk budget is a sum of money included in the
[ ? ] and set aside to fund specific management responses to a project's threats and opportunities
B
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and
procedures which ensure that the [ ? ] created meet(s) the needs of the business.
B
Which is NOT considered when defining risk tolerance?
B
Which statement about the quality review technique is FALSE?
B
Which should be provided by corporate or programme management before the Starting up a Project
process commences?
B
Why is it crucial that the Project Product Description clearly defines acceptance methods?
C
Which of the following statements about customer's quality expectations and acceptance criteria are
true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a
project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding
of general quality requirements.
D
Which is part of quality control?
A