pmi pmi-acp practice test

Exam Title: PMI Agile Certified Practitioner

Last update: Dec 26 ,2025
Question 1

More details for a story are required before the upcoming sprint planning meeting What should the
scrum master do?

  • A. Email the product owner requesting detailed story specifications and wait for a response
  • B. Gather the details from the team members before sprint planning
  • C. Schedule a story grooming session with the product owner before sprint planning
  • D. Conduct a planning poker session with the team
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 2

During planning sessions an agile practitioner notices that some team members do not share
common ideas What should the agile practitioner do?

  • A. Ask the team if they would like to adopt alternative techniques
  • B. Create a team norms document to set participation guidelines
  • C. Ask the scrum master to resolve the issue at the stand up meeting
  • D. Capture feedback during lessons learned at the end of the iteration
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 3

What should an agile practitioner do to ensure that the end product meets business requirements?

  • A. Invite the team to iteration review meetings
  • B. Obtain agreement from the product owner on business requirements
  • C. Request that regular reports are sent to stakeholders.
  • D. Confirm managers and stakeholders are invited to product review meetings
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 4

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high
priority user stories into the iteration backlog. What should the team do first to define the tasks
needed to implement the user stories?

  • A. Self-organize
  • B. Assign tasks to each team member
  • C. Meet with the customer
  • D. Identify the Scrum Master
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 5

A company has decided to combine two similar products consisting of multiple teams into one
product. Engaged customers want to know how the company is looking at re-organizing it's teams.
What strategy should be employed to re-organize the teams?

  • A. All the teams from both products should be simultaneously called together and allowed to completely self-manage
  • B. Teams that worked on similar components in the separate products should be combined to minimize disruption andcapitalize on synergies
  • C. After grouping individuals by role multi-discipline teams should be created that are comprised of one member from eachrole
  • D. Features should be prioritized and then teams should be organized around those priorities
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 6

During a current sprint, a team member asks permission from the scrum master to investigate an
alternative design approach What should the scrum master do?

  • A. Discourage the team member from deviating from the plan and document the request during the retrospective
  • B. Encourage the team member to research the issue and present the findings during the retrospective
  • C. Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases
  • D. Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important.
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 7

Midway through a sprint, the scrum master identifies that reassigning a certain task could help the
team meet its sprint goals What should the scrum master do next?

  • A. Alert the team that sprint goals might not be met and create an alternative plan
  • B. Obtain team buy-in to perform modifications to the sprint backlog.
  • C. Have the sprint proceed as planned
  • D. Ask the team to decide if the task should be reassigned
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 8

A technical problem arises that will likely impact the stories planned for delivery in the current sprint
What should the scrum master do?

  • A. Consider adding a story to the next sprint to seek resolution
  • B. Immediately solve the problem on behalf of the team
  • C. Ask the team to collaboratively work out a solution.
  • D. Engage a technical manager to assist with finding a solution
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 9

An executive sponsor of a new scrum team actively attends scrum ceremonies How does this benefit
the team?

  • A. It helps the team to focus on and meet sprint goals.
  • B. It reminds the team about who sponsors the project.
  • C. It provides high-level project updates to the sponsor
  • D. It helps to quickly resolve issues using the sponsor's Influence
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 10

When prioritizing features to be delivered in an iteration, on what features should an agile team
defer work?

  • A. High-risk and high-value
  • B. High-risk and low-value
  • C. Low-risk and low-value
  • D. Low-risk and high-value
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Page 1 out of 48
Viewing questions 1-10 out of 482
Go To
page 2