IIBA iiba-aac practice test

Exam Title: Agile Analyst

Last update: Dec 30 ,2025
Question 1

Making decisions based on a realistic understanding of current organizational strengths, capabilities,
and challenges, is represented in the agile analysis principle of:

  • A. See the whole
  • B. Individuals and interactions over process and tools
  • C. Think as a customer
  • D. Understand what is doable
Answer:

A


Explanation:
Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(36)

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 2

During a team meeting, the team discuss a technique where real or perceived benefits to the
customer, direct costs and opportunity costs are assessed. Which technique are they discussing?

  • A. Minimum Viable Product
  • B. Impact Mapping
  • C. Kano Analysis
  • D. Value Modeling
Answer:

D


Explanation:
Value Modelling models value creation for stakeholders who use the solution. Value Modelling is also
referred to as Customer Value Model. Value Modelling follows a basic structure: Customer value =
Benefits – Cost Benefits can be real (solves a problem or completes a job) or perceived (increases
status, reputation, likability).

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 3

At the Initiative Horizon, the solution owner using iterative planning principles decides to plan for a
period of:

  • A. 6-12 months because competitive analysis requires thorough analysis
  • B. 1-3 months because it can be determined if needs are being met
  • C. 3-6 months because stability is required for long term planning
  • D. 1-2 weeks because it aligns with the increments delivered by the team
Answer:

B


Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(46)

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 4

Planning horizons are important because they allow an organization to:

  • A. Support a structured response supported by all levels of the organization
  • B. Sense and respond to their changing environment
  • C. Ensure senior management is informed and engaged
  • D. Allow management guidance for decision making
Answer:

B


Explanation:
In constant and rapidly changing environments, organizations are required to be able to sense and
respond to local opportunities and problems without the need to involve the whole organization,
while also looking forward at emerging threats and opportunities. These planning horizons provide a
framework for the shift in focus that occurs when moving between understanding the long-term
strategic needs of the organization and the immediate needs of a customer.

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 5

The team is creating plans at the Strategy Horizon. Diverse opinions are delaying this effort because
different people are focused on different timeframes. After some discussion the team realizes they
need to focus their efforts on the following viewpoint:

  • A. Business view of the teams working on the initiatives
  • B. Micro-view of the potential changes to the organization
  • C. Broader view of the impact of the change to the organization
  • D. Local view of the effect on the community.
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 6

The team is expanding and refining customer scenarios as the solution components are being
developed. This is an application of the following agile business analysis principle:

  • A. Understand what is doable
  • B. Avoid waste
  • C. Stimulate collaboration and continuous improvement
  • D. Get Real Using Examples
Answer:

C


Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(21)

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 7

In situations where learning is frequent and fast-paced, and the product owner is reacting to the new
information, the prioritization of solution components should be expected to:

  • A. Be unaffected
  • B. Remain stable
  • C. Alter intermittently
  • D. Change frequently
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 8

While quality checking the written user stories, the team ensures one of the components included in
the attributes of a user story is:

  • A. The explanation of the story’s cost
  • B. The stakeholder responsible for testing
  • C. The benefit or business value received by the user when the story is implemented
  • D. The title describing the goal of the delivery cycle
Answer:

C


Reference:
https://www.yodiz.com/blog/user-story-characteristics-in-agile-scrum-methodology/

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 9

Members of the team facilitate key stakeholders through an exercise to develop a mutual
understanding of what is in and out of scope for the initiative and specify the organization value to
achieve in the initiative. What technique did they use?

  • A. Sprint Goals
  • B. Visioning
  • C. Purpose Alignment Model
  • D. Story elaboration
Answer:

A


Reference:
https://www.visual-paradigm.com/scrum/write-sprint-goal/

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 10

A product owner has selected a particular workflow, and needs to identify potential epics and
initiatives to learn more about it. They gather a group together to visually identify activities and
themes of possible interest. What technique is typical for this purpose?

  • A. Value stream mapping
  • B. Cartesian mapping
  • C. Story Mapping
  • D. Data flow mapping
Answer:

C


Reference:
https://blog.easyagile.com/anatomy-of-an-agile-user-story-map-4ecb6a508d94

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Page 1 out of 8
Viewing questions 1-10 out of 85
Go To
page 2