Question 1

Your customer has the following HPE Synergy setup
- 3 HPE Synergy 12000 Frames
- 4 HPE Virtual Connect SE 100 Gb F32 Modules
- 2 HPE Synergy 50 GO Interconnect Link Modules
- 36 HPE Synergy 480 Gen10 Plus compute modules
- 2 HPE Composer 2 modules
Which statement about this setup is true?

  • A. To use all compute nodes, the customer must create at least two logical enclosures
  • B. To manage all frames, the customer must buy two additional HPE Composer 2 modules
  • C. The customer must buy 36 HPE OneView Advanced licenses to manage compute modules
  • D. The customer can add one D3940 storage Module to each of the frames
Answer:

C


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 2

HOTSPOT
An HPE Synergy customer needs to prevent a timeout and loss of communication during an external
switch firmware upgrade.
Click the parameter that the customer should configure within an uplink set to meet this
requirement

Answer:

None


Explanation:

vote your answer:
Comments
Question 3

Which statement about HPE Superdome Flex 280 is true?

  • A. It supports 2 to 8 sockets in 2-socket increments.
  • B. it cannot be managed using HPE OneView.
  • C. It must be equipped with at least 768 GB of memory.
  • D. It can support up to two nPars with an external RMC.
Answer:

C


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 4

You are troubleshooting an HPE OneView server profile that presents a critical state. The server
profile was configured with a Link Aggregation Group
What should you check to fix the issue?

  • A. if both FiexNICs are configured with the same speed
  • B. If the logical enclosure is built on at least three HPE Synergy frames
  • C. if both FiexNICs are connected to different networks
  • D. if the logical enclosure is configured with redundant master modules
Answer:

A


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 5

Your customer experienced some problems caused by outdated HPE Superdome Flex firmware.
Which update method should they use to avoid these issues in the future?

  • A. HPE OneView method for I/O firmware update procedure
  • B. RMC CLI to update I/O and HPE Persistent Memory firmware
  • C. HPE OneView IT HPE Persistent Memory firmware must be updated.
  • D. HPE SUM if HPE Persistent Memory firmware must be updated
Answer:

B


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 6

Your customer needs to move an application from an HPE Synergy 480 Gen10 Compute Module to an
HPE Synergy 660 Gen 10 Compute Module. The 480 has a switch that has been manually zoned
outside of HPE OneView.
What must the customer do before migrating the application?

  • A. Migrate the application to a Logical JBOD and connect it to the new server
  • B. Copy the server profile and assign the clone to the new hardware
  • C. Edit the server profile and change server hardware type
  • D. Create a new server profile template and apply to the new hardware
Answer:

C


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 7

Your customer has me following HPE Synergy setup
- Three frames fully populated with HPE Synergy 480 Gen10 Plus modules and 25Gb/s downlink
speed formulating a single logical enclosure
- Two HPE Virtual Connect SE 100Gb F32 Module for Synergy
- Four HPE Synergy 50Gb interconnect Link Module
- Six HPE Synergy Virtual Connect SE 32Gb FC Modules
The customer needs to add a frame.
Which statement about the expansion of this setup is true?

  • A. The additional frame must have HPE Virtual Connect FC modules installed
  • B. The customer can grow the existing logical enclosure up to 5 frames
  • C. The customer has to create a new logical enclosure for the additional frame
  • D. The additional frame cannot have 12Gb SAS connection modules installed
Answer:

C


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 8

HOTSPOT
Click the area within the iLO management interface that will allow you to access workload Advisor.

Answer:

None


Explanation:

vote your answer:
Comments
Question 9

Your customer plans to deploy HPE OneView for VMware vCenter Server together with HPE Storage
Integration Pack for VMware vCenter. The customer wants to use them to manage HPE Synergy
Gen10 compute modules. HPE ProLiant Gen 10 servers and an MSA array.
Which statement about compatibility of the existing environment with the planned software
components is true?

  • A. Both HPE Synergy Gen10 full-height compute module plugins will require a license
  • B. HPE OneView for VMware vCenter Server does not support standalone HPE ProLiant servers
  • C. To use the required plugins HPE ProLiant Gen10 systems must be managed using HPE OneView
  • D. HPE Storage integration Pack for VMware vCenter does not support MSA arrays
Answer:

B


vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 10

Refer to the exhibit.

Which statement about this logical interconnect group is true?

  • A. Both modules are located in different frames for redundancy
  • B. For an uplink set, ports from different modules can be selected
  • C. interconnect modules are installed in interconnect bays 1 and 4
  • D. An additional license is required to change the enclosure count