Question 1

Which input to the Manage Stakeholder Engagement process is used to document changes that
occur during the project?

  • A. Issue log
  • B. Change log
  • C. Expert judgment
  • D. Change requests
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 2

An input to the Plan Stakeholder Management process is:

  • A. The project charter.
  • B. The stakeholder analysis.
  • C. A communication management plan.
  • D. A stakeholder register.
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 3

An input to the Plan Cost Management process is:

  • A. Cost estimates.
  • B. Resource calendars,
  • C. The project charter,
  • D. The risk register.
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 4

A technique used to determine the cause and degree of difference between baseline and actual
performance is:

  • A. Product analysis.
  • B. Variance analysis.
  • C. Document analysis,
  • D. Decomposition.
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 5

The process of identifying and documenting project roles, responsibilities, required skills, and
reporting relationships and creating a staffing management plan is known as:

  • A. Develop Project Team.
  • B. Manage Project Team.
  • C. Acquire Project Team.
  • D. Plan Human Resource Management.
Answer:

D

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 6

Which type of dependency is legally or contractually required or inherent in the nature of work and
often involves physical limitations?

  • A. Mandatory
  • B. Discretionary
  • C. Internal
  • D. External
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 7

During which process does a project manager review all prior information to ensure that all project
work is completed and that the project has met its objectives?

  • A. Monitor and Control Project Work
  • B. Perform Quality Assurance
  • C. Close Project or Phase
  • D. Control Scope
Answer:

C

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 8

An input to the Manage Project Team process is:

  • A. Work performance reports.
  • B. Change requests.
  • C. Activity resource requirements.
  • D. Enterprise environmental factors.
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 9

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

  • A. Procurement statement of work
  • B. Purchase order
  • C. Source selection criteria
  • D. Bidder conference
Answer:

A

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments
Question 10

A large portion of a projects budget is typically expended on the processes in which Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing
Answer:

B

vote your answer:
A
B
C
D
A 0 B 0 C 0 D 0
Comments