Which of the following steps should be first in determining operation start dates for capacity
planning?
B
A work center has one machine that is operated for one shift per day. The shop runs an 8-hour shift 5
days per week. Machine utilization has been 60% with efficiency at 80%. A routing through this work
center has a standard run time of .10 hours per piece. Job number 1234 is for 200 pieces. If the
utilization is improved to 80%, the difference in calculated lead time for the job is how many days?
B
The average length of time a job must wait at a work center is a function of the:
C
When an order is split into two orders, the immediate effect on a job shop work center is to increase
which of the following elements?
A
A supplier of roller bearings makes lots of 10,000 and sorts them automatically according to size. In
a typical lot of 10,000, the sizes break into the categories:
The product requires rollers on target or, at most, 0.0001 oversize. Experience indicates that 100%
must be reinspected before use because the machine inspection lets a few defective units slip
through. The supplier should be encouraged to take which of the following actions?
A
If an operation on a routing is performed out of sequence and the change in sequence is not
reported to the formal system, which of the following situations will occur?
C
In a continuous flow environment, it is necessary to report which of the following data from the shop
floor?
C
The actual output of a work center for a given time period can be determined by evaluating the:
B
Which of the following project characteristics would suggest using the PERT technique, rather than
the critical path method?
A
Statistical process control is a technique primarily used to:
B